# Renovation Scope of Work

Copy this template and complete the sections relevant to your project. Delete anything that does not apply.

## 1. Project details

- Project name:
- Property address:
- Property type and approximate age:
- Client contact:
- Preferred start date:
- Required completion date:
- Quotation deadline:

## 2. Objectives and constraints

- What should the project achieve?
- What must remain unchanged?
- Which drawings, photographs and reports are attached?
- Are there known defects, damp, movement or previous alterations?
- Will the property remain occupied during the work?

## 3. Scope by room or area

Repeat this section for every room.

### Room/area:

**Demolition and removal**

- What will be removed?
- What will be retained or reused?
- Who removes and pays for waste?

**Construction and finishes**

- Walls:
- Ceiling:
- Floor:
- Doors, trim and fitted furniture:

**Services and specialist work**

- Electrical:
- Plumbing and drainage:
- Ventilation and heating:
- Structural work:

**Installation and completion**

- Products to install:
- Decorating, sealing and finishing:
- Cleaning and making good:

## 4. Materials and products

| Item | Manufacturer/model | Colour/finish | Quantity | Supplied by | Acceptable alternative |
|---|---|---|---|---|---|
|  |  |  |  |  |  |

State how substitutions must be approved before ordering.

## 5. Responsibilities and interfaces

- Who is the main site contact?
- Who coordinates subcontractors?
- Who applies for approvals and permissions?
- Who books inspections and testing?
- Who protects existing finishes and common areas?
- Who provides power, water, welfare facilities, parking and access?
- Who receives and stores deliveries?

## 6. Price and payment

- Pricing basis: fixed quotation / estimate / day rate / cost plus
- Is VAT included?
- Which allowances or provisional sums remain open?
- Day rates and material mark-ups for variations:
- Payment stages and measurable milestones:
- Amount retained until defects are corrected, if agreed:

## 7. Programme

| Milestone | Planned date | Responsible party | Dependency |
|---|---|---|---|
| Start on site |  |  |  |
| Demolition complete |  |  |  |
| Concealed services inspected |  |  |  |
| Walls and floors closed |  |  |  |
| Installation complete |  |  |  |
| Handover |  |  |  |

## 8. Variations

No additional work proceeds until the following are agreed in writing:

- description of the change
- reason for the change
- price
- effect on the completion date
- person authorised to approve it

## 9. Handover documents

Select what must be supplied:

- [ ] Final invoices and payment record
- [ ] Photographs of concealed work before covering
- [ ] Electrical and other compliance certificates
- [ ] Test and commissioning records
- [ ] Product manuals and maintenance information
- [ ] Warranties and serial numbers
- [ ] Updated drawings
- [ ] Planning and building-control records where relevant
- [ ] Snagging and defect-completion list

## 10. Exclusions

-
-

## 11. Assumptions and clarifications

-
-

## 12. Acceptance

- Quotation/contract reference:
- Date:
- Client:
- Contractor:

This is a practical working template, not a substitute for legal advice or a suitable building contract.